Two flow numbers that must not be merged
A forced-circulation package has a net production rate and a circulating flow. The feed and concentrate streams set the material balance; the circulation stream keeps the heater and separator supplied. The Tetra Pak Dairy Processing Handbook's circulation-evaporator example recirculates a large volume and gives a chamber flow four to five times the inlet flow for that dairy case. The example illustrates why the numbers are separate; it is not a circulation ratio to copy into a fruit project.
State the capacity basis in kg/h of feed, concentrate and evaporated water at defined compositions and temperatures. If a volume is quoted, give density and temperature. Do not describe circulation-pump flow as feed capacity or evaporation capacity. A proposal that mixes these quantities cannot be compared with another proposal on the same duty.
Put the takeoff at a physical boundary
The takeoff boundary should be drawn on the process flow diagram. It includes the separator outlet, level control, concentrate discharge route, any concentration trim and the transfer to storage or the next process. The Tetra Pak example lists a balance tank, feed pump, preheating, vacuum chamber, recirculation pump and vacuum pump as parts of a process line; the exact scope of a project still has to be stated. The same is true here: the diagram must show what is supplied and what is by others.
Decide whether the boundary ends at the separator, at a discharge pump, at a storage-tank connection or at another agreed flange. Identify sampling points, drains, vents and cleaning returns. A clear boundary makes it possible to assign pressure, temperature and concentration conditions to the correct piece of equipment.
Give the discharge route its own duty
Concentrated product can be more viscous and more difficult to pump than the feed. The discharge route therefore needs its own flow, pressure and suction conditions. Record the expected viscosity and temperature at takeoff, the static lift, line length, fittings and the pressure at the receiving point. Check restart after a stop and the behaviour of any product that cools in the line.
The route also needs a cleaning and drainage concept. Identify low points, the return path to the CIP circuit and how the line is isolated from product. A pump selected only for water or for the feed stream does not establish performance on the concentrate. The proposal should state the pump duty point and the conditions under which it is guaranteed.
Line sizing should use the same product basis as the pump duty, including any required minimum velocity and the pressure available at the receiving vessel. If the route can be drained by gravity, say so; if it needs flushing or pigging, include the utility and recovery path. These details affect both the installed layout and the cleaning procedure.
Connect instrumentation and control to the boundary
Level, pressure, temperature, flow and concentration measurements should be tied to the control actions they support. If the separator level falls, which stream is adjusted? If concentration drifts, where is the corrective action applied? If circulation is lost, what happens to feed and heating? The answers define the control boundary as much as the piping does.
Sampling is part of the same decision. State whether samples are taken from the circulating loop, the discharge line or a dedicated point, and how the sample represents the product at that moment. A concentration measurement used for control needs a defined method, location and update interval. Do not assume that a single reading represents the whole inventory.
State capacity, utilities and acceptance on one sheet
A comparable proposal sheet should list the feed and concentrate basis, net water removal, circulation flow and pressure rise, heating duty, cooling duty, electrical demand and operating hours. It should also state the utility conditions at the boundary, the required product-quality checks and the operating range to be demonstrated. The UNIDO small-scale processing guide is useful for the wider production and quality-assurance context, but it does not substitute for a project-specific equipment schedule.
Distinguish guaranteed values from estimates and from values supplied by others. Include start-up, cleaning and part-load conditions if they affect the acceptance test. If a figure depends on a product property that has not been measured, say so and identify the trial needed to establish it.
A boundary that can be reviewed
A good takeoff boundary lets a reviewer trace one kilogram of feed through the package: where it enters, how it circulates, where water leaves, where concentrate is withdrawn and where the product stream ends. It also shows which measurements, controls and utilities support that path.
That level of definition does not guarantee a particular performance. It does make the proposal reviewable, comparable and testable. Start with the product history and the mass balance, then draw the takeoff boundary before comparing equipment prices.
Primary sources and scope
- Tetra Pak Dairy Processing Handbook, Chapter 7.6: EvaporatorsProcess-line components, recirculation-flow example and the separation of feed, circulation and vapour streams.